Healthcare construction revenue in this case represents earned completed-equivalent progress, not a whole new building sold each month. The fictional contractor allocates one progress-area pool across distinct work types and buys field trades separately. Profitable earned work still requires substantial cash before progress fees are collected.
Translate the progress proxy into actual released work packages, purchased commitments and accepted billing dates. The area calculation cannot establish site readiness, healthcare approval or cash availability.
What is a progress-square-foot equivalent?
The case is a healthcare-facility general contractor working in Virginia and Maryland, with actual jurisdictions and sites unselected, during January 2027–December 2029. It covers hospital additions, ward renovations, clinics, diagnostic suites and behavioral-health facilities. Client land, medical equipment, hospital operations and speculative development are excluded.
The selected capacity is 2,000 progress-square-foot equivalents per month. At 55% utilization it earns 1,100 equivalents after ramp. An equivalent is a way to represent completed progress over time; it is not the physical start or finish of an entire building. A real programme must reconcile the proxy to its work packages and evidence of accepted progress.
How does progress turn into earned fees?
Five distinct work types allocate the 1,100 earned equivalents once. Each has an inclusive fee per progress square foot reflecting its selected construction scope. The table therefore shows $583,000.00 of monthly earned fees, not the value of five new whole buildings or an annual contract value repeated monthly.
Purchased materials, trade subcontractors, rented/site services, protection/waste and permits/testing are direct categories. Field-trade labor is not also charged as an internal employee crew. Client medical equipment stays outside both the earned fee scope and contractor purchases in this scenario.
| Work type | Earned progress equivalents | Fee/progress sq ft | Earned fees |
|---|---|---|---|
| Additions | 220 | $850.00 | $187,000.00 |
| Ward renewal | 275 | $550.00 | $151,250.00 |
| Clinics | 330 | $300.00 | $99,000.00 |
| Diagnostics | 165 | $650.00 | $107,250.00 |
| Behavioral | 110 | $350.00 | $38,500.00 |
What does the retained payroll actually provide?
The paid roster includes two project managers, two site superintendents, the owner managing director, an estimator and half-time project administration. Those people coordinate and supervise purchased work. Their payroll does not mathematically convert to the assumed progress area or prove coverage for all simultaneous workfronts.
Before promising a package, establish its design/site release, specialist responsibilities, trade availability, supervision, checking and acceptance. The financial case establishes none of the actual permits, technical completion or occupancy conditions. Its capacity proxy needs an executable project schedule rather than a larger area multiplier.
Why does positive earned progress still need a reserve?
March earns $583,000.00 and reports EBITDA of $31,742.75, but receives $291,500.00. Operating cash flow is -$225,783.90. The 45-day collection assumption sits beside ten supplier payment days and seven inventory days, so purchased work and materials can require cash before accepted progress becomes receipts.
First-year net income is $181,879.23 while operating cash flow is -$502,487.43. Proposed uncommitted equity totals $2,596,747.82; no debt is modeled. Startup uses are $248,910.34 and forecast minimum cash is $1,639,882.53. The larger funding amount includes liquidity rather than additional startup expense.
What should the first work package prove?
Take one released package and map its scope to actual quantities, trade commitments, material payments, supervised work, accepted progress and receipt dates. State which client-owned items and other packages are excluded. Do not assume a deposit or advance: customer prepayments are outside the saved scenario.
Compare the package’s earned progress with both the real resource schedule and its cash exposure before accepting overlapping sites. If progress certification or a purchased scope moves, update the dated funding plan. An annual profit figure cannot finance a particular trade payment until usable cash is available.
Make the next decision with your own evidence
Build a released work-package schedule linking purchased trades/materials to supervised progress, acceptance and collected fees, excluding client land and medical equipment throughout.
Explore published business plan examples ↗Carefront Builders is a fictional prelaunch scenario prepared with AI assistance. Inputs are illustrative; forecast results come from the matching saved financial model. Funding is proposed. The diagrams explain the case and do not depict actual premises, established demand or promised earnings. Replace the assumptions with evidence before committing.